Chicago Demolition Utility Disconnect: Who Shuts Off What?

The utility company does not handle everything. The City's checklist puts sewer and water on the demolition permit. Gas and electric need their own confirmation.

Short answer

Two utilities are on the City's demolition checklist: sewer and water. A Water Management sewer disconnection (cut and seal) permit or written determination is required, and the water cut and seal permit is pulled by a licensed plumbing contractor. Gas and electric are not listed among the demolition approvals on the City page we read, so do not assume a City step exists. Confirm gas and electric disconnection with the Department of Buildings and your utilities.

A common assumption on a Chicago teardown is that you call the utility, they shut everything off, and the City is not involved. For sewer and water, the City's checklist says otherwise. For gas and electric, we cannot point to a City requirement, and we will not make one up.

What does the City require for sewer and water?

The City's demolition approval checklist includes two utility items, both needed before a permit issues (City of Chicago):

"Cut and seal" means the line is cut at the building and sealed, so the old connection does not stay open to the ground and the sewer. The City's Department of Buildings page requires those permits and an inspection (City of Chicago). So the plumbing contractor is on the job before the demolition crew, not after.

That also tells you who is who. The demolition has to be done by a City-licensed general contractor, but the water cut and seal is pulled by a plumbing contractor. Ask your demolition contractor whether they have a plumber lined up or expect you to find one. Our demolition contractor guide covers what to ask.

What about gas and electric?

This is where we stay careful. The City's demolition page lists water and sewer cut and seal among the approvals. In the text we read, it does not list gas or electric disconnection as a demolition approval (City of Chicago). The Building Code does include a utility connections section among the items a site safety plan must address, which means the topic is not ignored. But we cannot give you a specific City permit step for it.

So the honest answer is: confirm gas and electric disconnection with the Department of Buildings (DOB) and with your gas and electric utilities before demolition starts. Do not assume the demolition permit covers it, and do not assume the crew can cut a live service. A live gas or electric service on a building that is coming down is a safety problem, and it is one to settle in writing.

How to sequence it so nothing stalls

  1. Ask your contractor for the utility plan in writing: who handles sewer, water, gas and electric, and in what order.
  2. Confirm with the DOB which utility items your permit needs. The list changes, and as of August 10, 2026 demolition applications go through the City's Inspection, Permitting and Licensing Portal, so older instructions may be out of date.
  3. Contact your gas and electric utilities directly for their disconnection steps and any lead time. We are not stating a timeline because we have not verified one.
  4. Keep the sewer and water permits and inspection records with the demolition file. They are part of what the City checks.

For the full list of approvals around these items, see Chicago demolition permit requirements, or print the permit checklist. The house demolition guide covers the whole sequence, and our demolition crew coordinates the trades so utility work is done before the machine shows up.

Common questions

Not necessarily. For sewer and water, the City's checklist requires cut and seal permits and an inspection, and the water permit is pulled by a licensed plumbing contractor. For gas and electric, confirm the steps with the Department of Buildings and your utilities.

A licensed plumbing contractor pulls the water disconnection (cut and seal) permit, according to the City's checklist. The sewer disconnection permit or written determination comes from Water Management.

We could not confirm one. The City's demolition page we read lists sewer and water cut and seal but not gas or electric. Confirm with the Department of Buildings and your utilities before work starts.

Where to go from here

Sources

  1. City of Chicago, Department of Buildings: Demolition (Wrecking) Permits

Facts last checked: October 7, 2026.

This article explains general rules and common situations in Chicago. It is not legal advice, and City rules change. For a specific property, check with the Chicago Department of Buildings or a licensed professional.

Talk to Akats

Planning a teardown?

Akats handles house and garage demolition in Chicago, including the permit checklist and utility coordination.

Request a Free Estimate

Tell us about the property. No obligation.

Free estimates subject to scope of project. We typically respond within one business day.

Call Free Estimate →