Chicago Demolition and Asbestos: What Must Happen First

You can demolish a house that has asbestos. You cannot skip the City's notices first. Here is what CDPH requires and where it fits in the permit.

Short answer

Yes, a Chicago house with asbestos can be demolished, but the City's health department has to be notified first. A Demolition Notice of Intent goes to the Chicago Department of Public Health at least 10 working days before any non-emergency demolition starts, and it is on the permit checklist. A separate asbestos abatement notice has the same 10 working day lead time for any building except a single-family home.

If you want to demolish a house with asbestos in Chicago, the answer is yes, with notice first. The City does not forbid it. It requires that the Chicago Department of Public Health (CDPH) hear about the demolition ahead of time, so dust and hazardous material are handled before anyone swings a machine.

This article covers the asbestos and dust notices only. For the full list of approvals, see Chicago demolition permit requirements, and for the whole process start with our Chicago house demolition guide.

What does Chicago require before a demolition with asbestos?

Two City rules are in play, and both run through CDPH.

The Demolition Notice of Intent. CDPH says a Demolition Notice of Intent must be submitted through the City permit portal at least 10 working days before the start of any non-emergency demolition. The notice is about dust and asbestos or other hazardous material measures. It is not optional paperwork. The Department of Buildings' own checklist of approvals needed before a wrecking permit issues begins with the CDPH Demolition Notice of Intent.

The Notice of Asbestos Abatement. CDPH also says a Notice of Asbestos Abatement must be submitted at least 10 working days before work that disturbs any amount of asbestos in any building except single-family homes. The code sections CDPH cites run from 11-4-2150 to 11-4-2190 of the Municipal Code of Chicago.

Two details to notice. First, the notice period is counted in working days, not calendar days. Second, the abatement notice carves out single-family homes, but the Demolition Notice of Intent does not. A single-family house still needs the Demolition Notice of Intent filed. Rules like these change, so confirm the current requirements with CDPH before you plan the schedule.

Who checks a house for asbestos?

We cannot cite a City rule that spells out who tests or what testing is required for a particular house, so we will not invent one. What we can say is that the City treats asbestos and dust as a pre-permit item, and that the Department of Buildings also lists asbestos notification and dust control as requirements that apply regardless of any permit exemption.

In practice, ask two questions at the start of any older house demolition: has anyone checked for asbestos-containing material, and who is responsible for filing the CDPH notices? If the answer from a contractor is a shrug, find a different contractor. Ask CDPH what it expects for your property.

Where does the CDPH notice fit in the demolition permit?

It is one item on a longer list. Per the Department of Buildings' pre-permit checklist, a Chicago wrecking permit also needs approvals such as rodent control, a public right-of-way permit or written no-permit determination, sewer and water cut-and-seal permits, Department of Housing approval for buildings with dwelling units, and historic preservation review for orange or red buildings in the Chicago Historic Resources Survey.

And since August 10, 2026, demolition applications go through the City's Inspection, Permitting and Licensing Portal. Applications started under the old process before August 6, 2026 may continue until December 30, 2026. If a contractor's website still describes the old email and Form 480 process, it is out of date.

The CDPH notice is also on a clock. The 10 working day lead time means you plan for it on day one, not the week before you want to start. We do not promise permit timelines, because several offices work in parallel and your building's facts decide what applies. But we can say this: a late CDPH notice is a self-inflicted delay. See what slows a Chicago demolition permit down.

Who files it

A wrecking contractor usually handles the portal filing. But the permit applicant has to be a property owner, and the demolition must be done by a City-licensed general contractor. Know who is filing what.

Who does this apply to?

What it means in practice

Plan the sequence backward from your start date:

  1. Have the building looked at for asbestos-containing material before you set a schedule.
  2. Decide who files the CDPH notices.
  3. File the Demolition Notice of Intent through the City portal, and the abatement notice if your building is not a single-family home.
  4. Work the other pre-permit approvals in parallel. See Chicago demolition rodent control, which has its own inspection.
  5. Plan what happens to the debris. After the work, recycling paperwork goes to CDPH, and 50 percent of recyclable debris must be recycled. See where Chicago demolition debris goes.
What we see in Chicago

On older Chicago buildings the surprise is rarely that asbestos exists. It is that nobody wrote down who was supposed to find it. Owners assume the demolition contractor will handle it. The contractor assumes the owner did a survey. The notice period starts late and the start date moves.

What happens if you ignore it

Skipping or filing the CDPH notices late can hold up the wrecking permit, since the Demolition Notice of Intent is a pre-permit approval. Starting work without them invites enforcement, and disturbing asbestos without following the rules exposes your crew, your neighbors and you. The City treats dust and asbestos as public health items, not paperwork. Talk to the Department of Buildings or CDPH about your specific situation.

Akats runs house demolition in Chicago with City paperwork handled as part of the job. If you are weighing a teardown on an older house, call us at 312-339-9627 and we will walk through what has to be filed first.

Common questions

Yes, but the City requires notice first. A Demolition Notice of Intent goes to CDPH through the City permit portal at least 10 working days before any non-emergency demolition, and a separate asbestos abatement notice has the same lead time for buildings other than single-family homes.

At least 10 working days before a non-emergency demolition starts, per CDPH. That is working days, not calendar days. Confirm the current requirement with CDPH when you schedule, because City rules change.

CDPH's abatement notice rule applies to any building except single-family homes. The Demolition Notice of Intent is separate and still applies. Check with CDPH about your specific house before you plan the work.

Yes. The Department of Buildings' pre-permit checklist lists the CDPH Demolition Notice of Intent among the approvals required before a wrecking permit is issued, along with rodent control, sewer and water cut-and-seal, and others.

Where to go from here

Sources

  1. City of Chicago, Department of Public Health: Asbestos, Demolition and Renovation Notifications
  2. City of Chicago, Department of Buildings: Demolition (Wrecking) Permits
  3. City of Chicago: Guide to Building Permits: What Types of Work Do Not Require a Building Permit?

Facts last checked: October 7, 2026.

This article explains general rules and common situations in Chicago. It is not legal advice, and City rules change. For a specific property, check with the Chicago Department of Buildings or a licensed professional.

Talk to Akats

Planning a teardown?

Akats handles house and garage demolition in Chicago, including the permit checklist and utility coordination.

Request a Free Estimate

Tell us about the property. No obligation.

Free estimates subject to scope of project. We typically respond within one business day.

Call Free Estimate →